James and Shawna Larson vs. Tempe Gardens Townhouse Corporation

Case Summary

Case ID 17F-H1717038-REL-RHG
Agency ADRE
Tribunal OAH
Decision Date 2017-12-11
Administrative Law Judge Thomas Shedden
Outcome loss
Filing Fees Refunded $0.00
Civil Penalties $0.00

Parties & Counsel

Petitioner James and Shawna Larson Counsel Lisa M. Hanger
Respondent Tempe Gardens Townhouse Corporation Counsel Nathan Tennyson

Alleged Violations

A.R.S. § 33-1255(C); CC&R sections 9 and 9(b)

Outcome Summary

The ALJ dismissed the petition, ruling that the HOA acted reasonably and had the authority under the CC&Rs to require the removal of the homeowner's patio cover for necessary painting and repairs. The ALJ determined that because the patio cover is a limited common element, the Petitioners must bear the cost of removal and reinstallation according to A.R.S. § 33-1255(C).

Why this result: Petitioners failed to prove the HOA violated CC&Rs or acted unreasonably, and statutory law assigned the expense burden for the limited common element to the homeowner.

Key Issues & Findings

Authority of HOA to mandate removal of homeowner's patio cover for maintenance and assignment of removal/reinstallation costs.

Petitioners challenged the Respondent HOA's authority and reasonableness in requiring them to remove their patio cover, a limited common element, for building painting and repair, and disputed the requirement that Petitioners bear the costs. The ALJ concluded that the HOA's plan was reasonable, the HOA had the authority under CC&R sections 9 and 9(b), and Petitioners must bear the cost of removal and reinstallation under A.R.S. § 33-1255(C).

Orders: Petitioners’ petition is dismissed. Respondent is deemed the prevailing party. Petitioners are responsible for the cost to remove the patio cover and the cost to reinstall it should they choose to do so.

Filing fee: $0.00, Fee refunded: No

Disposition: respondent_win

Cited:

  • A.R.S. § 33-1255(C)
  • CC&R section 9
  • CC&R section 9(b)
  • A.R.S. § 33-1212(4)
  • Tierra Ranchos Homeowners Ass'n v. Kitchukov

Analytics Highlights

Topics: HOA authority, limited common element, maintenance costs, patio cover, CC&Rs, statutory interpretation, dismissal, prevailing party
Additional Citations:

  • A.R.S. § 33-1255(C)
  • CC&R section 9
  • CC&R section 9(b)
  • A.R.S. § 33-1212(4)
  • Tierra Ranchos Homeowners Ass'n v. Kitchukov
  • A.R.S. § 32-2199
  • A.R.S. § 32-2199.02
  • A.R.S. § 41-1092.09
  • ARIZ. ADMIN. CODE § R2-19-119
  • Gutierrez v. Industrial Commission of Arizona

Video Overview

Audio Overview

Decision Documents

17F-H1717038-REL Decision – 583987.pdf

Uploaded 2025-10-09T03:31:46 (53.0 KB)

17F-H1717038-REL Decision – 585505.pdf

Uploaded 2025-10-09T03:31:46 (385.9 KB)





Briefing Doc – 17F-H1717038-REL


Briefing on Larson v. Tempe Gardens Townhouse Corporation

Executive Summary

This briefing synthesizes the legal dispute between homeowners James and Shawna Larson and the Tempe Gardens Townhouse Corporation (the “Respondent” or “HOA”). The core conflict centered on the HOA’s directive that the Larsons remove their wooden patio cover at their own expense to facilitate a community-wide building repair and painting project.

The case progressed through two distinct phases. Initially, an Administrative Law Judge (ALJ) recommended dismissing the Larsons’ petition for a lack of a “justiciable controversy,” reasoning that the HOA had not yet acted on its threat to remove the patio cover, rendering the dispute speculative. However, the Commissioner of the Department of Real Estate rejected this recommendation, finding the matter was “ripe for adjudication,” and ordered a full hearing on the merits.

In the final decision, a second ALJ dismissed the Larsons’ petition and ruled in favor of the HOA. The judge found the HOA’s plan to be reasonable and necessary for the proper and safe completion of the project, based on credible testimony from the project manager. The decision affirmed the HOA’s authority under its CC&Rs to require the removal of the structure. Crucially, the ruling established that the patio cover is a “limited common element” under Arizona law. Consequently, pursuant to Arizona Revised Statutes, the homeowners (the Larsons) are exclusively responsible for all costs associated with it, including its removal and potential reinstallation.

Procedural History and Jurisdictional Rulings

Initial Petition and Dismissal Recommendation

On June 16, 2017, James and Shawna Larson filed a petition with the Department of Real Estate against their HOA, alleging a violation of the community’s Covenants, Conditions, and Restrictions (CC&Rs). However, the initial filing did not specify which provisions had been violated.

Upon inquiry, the Petitioners’ counsel admitted via email that no specific provision of the CC&Rs had yet been violated. Instead, their concern was that section 10(a) would be violated if the HOA acted on its threat to forcibly remove their patio cover and charge them for the cost.

This led to the “ORDER RECOMMENDING DISMISSAL FOR LACK OF JUSTICIABLE CONTROVERSY,” issued on August 25, 2017, by Administrative Law Judge Suzanne Marwil. The key findings of this order were:

Speculative Harm: The Judge found that the HOA’s actions “have not yet been undertaken and our [are] speculative at this juncture.”

Lack of Jurisdiction: The order stated that the Office of Administrative Hearings’ jurisdiction, per A.R.S. § 32-2199, is limited to adjudicating existing violations of community documents, not potential future ones.

Misunderstanding by Both Parties: The order noted, “Both parties fundamentally misunderstand the limits of this Tribunal’s jurisdiction.” The Petitioners were seeking a ruling on a future action, while the Respondent was urging the Tribunal to find the Petitioners had violated the CC&Rs, which was not the subject of the petition.

Recommended Forum: The Judge suggested that the appropriate forum for the Petitioners would be a declaratory judgment action in superior court.

Rejection of Dismissal and Re-Hearing

On August 31, 2017, Judy Lowe, the Commissioner of the Department of Real Estate, issued an “ORDER REJECTING RECOMMENDATION OF DISMISSAL.”

• The Commissioner rejected the ALJ’s finding that the matter lacked a justiciable controversy.

• The order cited a letter from the Respondent dated June 1, 2017, which posed the question: “Is the presence of the awning a violation of the Association’s governing documents?”

• This question was deemed sufficient to make the matter “ripe for adjudication.”

• The Commissioner requested that the hearing be rescheduled for a ruling on the matter. A re-hearing was subsequently conducted on November 20, 2017, before Administrative Law Judge Thomas Shedden.

Analysis of the Merits of the Dispute

The re-hearing focused on the substantive conflict: whether the HOA had the authority to compel the Larsons to remove their patio cover at their own expense for the maintenance project.

Respondent’s (HOA) Case

The HOA, consisting of 169 units, initiated a project to make necessary repairs to its twenty-five buildings and then have them painted. The HOA’s position was based on the following points:

Legal Authority: The HOA asserted its authority under sections 9 and 9(b) of its CC&Rs, which state that the HOA is responsible for maintaining building exteriors and that “Any cooperative action necessary or appropriate to the proper maintenance and upkeep of the… [building] exteriors… shall be taken by the [Respondent].”

Project Necessity: The project manager, Wayne King, provided testimony that the HOA’s board deemed credible and reasonable.

Safety: King stated that all five bidding contractors required the patio covers to be removed to ensure a safe work environment as mandated by the Arizona Department of Occupational Safety and Health (OSHA).

Logistics: Standard scaffolding would not fit without removing the covers, commercial scaffolding would not provide full access, a forklift was not viable due to overhead power lines, and allowing painters to walk on homeowner patio covers was unsafe.

Quality of Work: The project involved sanding, power washing, and patching before painting to “do the job right.” Many covers had been improperly flashed, causing damage to the buildings that needed repair.

Warranty: The paint company would not provide a warranty for the project if individual homeowners, such as the Larsons, were permitted to paint their own units.

Petitioners’ (Larsons’) Case

The Larsons, who purchased their unit in 1999 with the wooden patio cover already in place, contested the HOA’s demands.

Challenge to Authority: The Petitioners argued that the HOA had no legal authority to demand the removal of their patio cover.

Unreasonable Cost: They asserted that the cost of removal and reinstallation was unreasonable, submitting two bids:

◦ One bid quoted $1,250 to remove and dispose of the cover and $3,980 to remove and rebuild it with new wood.

◦ A second bid quoted $5,975 to remove and then replace the structure.

Proposed Alternative: In a letter dated May 19, 2017, the Larsons offered to have the back of their unit painted at their own expense.

Compromise Offer: During the November 20, 2017 hearing, after hearing the project manager’s testimony, Ms. Larson offered that they would agree not to reinstall the patio cover if the HOA would pay for its removal.

Final Administrative Law Judge Decision

On December 11, 2017, ALJ Thomas Shedden issued a final decision dismissing the Larsons’ petition and finding in favor of the Respondent, Tempe Gardens Townhouse Corporation.

Key Findings and Conclusions of Law

Finding/Conclusion

Details

Standard of Review

The HOA’s decisions regarding maintenance and repair are given deference, provided they act reasonably.

Reasonableness of HOA Action

Based on the “credible testimony” of Wayne King, the Judge found that the HOA’s proposed plan for repairing and painting the buildings, which required the removal of patio covers, was reasonable.

HOA Authority

CC&R sections 9 and 9(b) were found to be “sufficient to show that Respondent has the authority to remove Petitioners’ patio to complete the painting work.”

Patio Cover Classification

The Petitioners’ patio cover was legally classified as a “limited common element” within the meaning of ARIZ. REV. STAT. section 33-1212(4).

Cost Responsibility

The central issue of payment was decided by statute. The Judge concluded that under a “reasonable reading of ARIZ. REV. STAT. section 33-1255(C),” any common expense associated with a limited common element “shall be assessed exclusively against the units benefitted.”

Final Order

Based on these findings, the Administrative Law Judge ordered the following:

“The evidence of record supports a conclusion that Respondent has authority to require Petitioners to remove their patio cover to allow the building to be properly and safely painted, and that Petitioners are responsible for the cost to remove the patio cover and the cost to reinstall it should they choose to do so.”

The final order was that the Petitioners’ petition be dismissed, and the Respondent, Tempe Gardens Townhouse Corporation, was deemed the prevailing party.






Study Guide – 17F-H1717038-REL


Study Guide: Larson v. Tempe Gardens Townhouse Corporation

This study guide provides a comprehensive review of the administrative case between homeowners James and Shawna Larson and the Tempe Gardens Townhouse Corporation. It includes a short-answer quiz, an answer key, suggested essay questions, and a glossary of key terms based on the provided legal documents.

——————————————————————————–

Short-Answer Quiz

Answer the following questions in 2-3 sentences each, based on the information in the provided source documents.

1. Who were the primary parties involved in this case, and what was their relationship?

2. What was the initial reason given by Administrative Law Judge (ALJ) Suzanne Marwil for recommending the dismissal of the Larsons’ petition?

3. Why did the Commissioner of the Department of Real Estate, Judy Lowe, reject the initial recommendation for dismissal?

4. What was the central dispute that was ultimately decided in the November 20, 2017, hearing?

5. According to the final Administrative Law Judge Decision, what is the legal classification of the petitioners’ patio cover?

6. Which specific sections of the CC&Rs did the Respondent, Tempe Gardens Townhouse Corporation, cite as the basis for its authority?

7. What key reasons did project manager Wayne King provide to justify the necessity of removing the patio covers for the painting project?

8. Describe the significant difference in the cost estimates for removing and replacing the patio cover as presented by the Petitioners versus the Respondent’s project manager.

9. What was the final ruling regarding who was financially responsible for the removal and potential reinstallation of the patio cover?

10. What was the ultimate outcome of the Larsons’ petition following the final hearing, and which party was deemed the “prevailing party”?

——————————————————————————–

Answer Key

1. The primary parties were the Petitioners, homeowners James and Shawna Larson, and the Respondent, the Tempe Gardens Townhouse Corporation, which is their homeowner’s association (HOA). The dispute arose from the HOA’s plan to repair and paint the building exteriors.

2. ALJ Marwil initially recommended dismissal due to a “lack of justiciable controversy.” She found that the Petitioners had failed to cite any provision of the CC&Rs that the Respondent had currently violated, as the threatened action to remove the patio cover was speculative and had not yet occurred.

3. Commissioner Lowe rejected the dismissal because she found the matter was “ripe for adjudication.” Her decision was based on a June 1, 2017 letter from the Respondent that questioned whether “the presence of the awning [is] a violation of the Association’s governing documents,” which she interpreted as the Respondent alleging a violation.

4. The central dispute was whether the Tempe Gardens Townhouse Corporation had the authority to mandate that homeowners, specifically the Larsons, remove their patio covers at their own expense to facilitate a building repair and painting project.

5. The final decision classifies the Petitioners’ patio cover as a “limited common element” within the meaning of ARIZ. REV. STAT. section 33-1212(4). This classification was crucial to determining financial responsibility.

6. The Respondent cited sections 9 and 9(b) of the CC&Rs. Section 9(b) makes the Respondent responsible for maintaining building exteriors, and section 9 grants it the authority to take “Any cooperative action necessary or appropriate to the proper maintenance and upkeep” of those exteriors.

7. Wayne King testified that removal was necessary to properly and safely complete the work using scaffolding, as required by modern safety laws. He also stated that removal was needed to repair improperly flashed areas behind the covers and to ensure the painting contractor would provide a warranty for the project.

8. The Petitioners presented bids showing the cost to remove and rebuild the cover would be between $3,980 and $5,975. In contrast, Mr. King opined these estimates were very high and that the cost should be closer to $1,000 if existing materials were reused.

9. The final ruling, based on ARIZ. REV. STAT. section 33-1255(C), was that the Petitioners must bear the cost of removing the patio cover and, if they choose, the cost of reinstalling it. This is because the patio cover is a limited common element assigned specifically to their unit.

10. The final outcome was the dismissal of the Larsons’ petition. The Respondent, Tempe Gardens Townhouse Corporation, was deemed the prevailing party in the matter.

——————————————————————————–

Essay Questions

The following questions are designed for a more in-depth analysis. Use the provided documents to construct a detailed, evidence-based response.

1. Trace the procedural history of this case from the initial filing to the final decision. Discuss the key turning points, including the initial recommendation for dismissal, its rejection by the Commissioner, and the reasoning behind the final judgment.

2. Analyze the legal arguments presented by both the Petitioners and the Respondent in the November 2017 hearing. On what specific statutes and CC&R provisions did each side rely, and how did the Administrative Law Judge ultimately interpret these documents?

3. Evaluate the role of expert testimony in this case, specifically focusing on the evidence provided by project manager Wayne King. How did his testimony regarding safety, project requirements, and cost estimates influence the Administrative Law Judge’s findings on the reasonableness of the Respondent’s actions?

4. Discuss the legal concept of a “limited common element” as defined and applied in the source documents. Explain how this classification was central to the final decision regarding financial responsibility for the patio cover’s removal and reinstallation.

5. The initial Administrative Law Judge found no “justiciable controversy,” while the Commissioner later found the matter “ripe for adjudication.” Based on the details in all three documents, explain the arguments for both positions and analyze why the case ultimately proceeded to a full hearing.

——————————————————————————–

Glossary of Key Terms

Definition from Source Context

Administrative Law Judge (ALJ)

An official in the Office of Administrative Hearings who adjudicates complaints regarding condominium and planned community documents and ensures compliance with relevant statutes.

Covenants, Conditions, and Restrictions. The documents that govern the community and are described as a contract between the homeowner’s association and the homeowners.

Justiciable Controversy

A real dispute that a tribunal has the authority to resolve. The initial petition was recommended for dismissal for a lack of a justiciable controversy because the Respondent’s threatened actions were deemed speculative.

Limited Common Element

A legal classification for property defined under ARIZ. REV. STAT. section 33-1212(4). In this case, the Petitioners’ patio cover was classified as such, meaning any common expense associated with its maintenance, repair, or replacement is assessed against the unit to which it is assigned.

Petition

The formal document filed with the Department of Real Estate to initiate a complaint against a homeowner’s association.

Petitioner

The party that files a petition initiating a legal action. In this case, the homeowners James and Shawna Larson.

Preponderance of the Evidence

The standard of proof required in this matter, defined as “The greater weight of the evidence… sufficient to incline a fair and impartial mind to one side of the issue rather than the other.”

Prevailing Party

The party that is successful in a legal dispute. In the final order, the Respondent was deemed the prevailing party.

Respondent

The party against whom a petition is filed. In this case, the Tempe Gardens Townhouse Corporation.

Ripe for Adjudication

A term used by the Commissioner of the Department of Real Estate to indicate that a dispute is ready to be formally heard and decided by the Administrative Law Judge.